Project Management: Planning, Execution, Evaluation and Control Nptel Week 4 Answers
Are you looking for Project Management Planning Execution Evaluation and Control Nptel Week 4 Answers ? All weeks solutions of this swayam course assignment are available here.
Table of Contents

Project Management Planning Execution Evaluation and Control Nptel Week 4 Answers (July-Dec 2025)
Course link: Click here to visit course on Nptel Website
Question 1. Use the network diagram and activity lengths in the nodes to determine the slack time for activity D.
a) 3
b) 2
c) 1
d) 0
Question 2. If activities C, E, and H are hammocked, what will be the duration of the hammock activity?
a) 19
b) 20
c) 21
d) 18
These are Project Management Planning Execution Evaluation and Control Nptel Week 4 Answers
Question 3. What is the estimated expected (mean) time for activity D?
a) 32 days
b) 41 days
c) 44 days
d) 42 days
e) 40 days
Question 4. What is the estimated standard deviation in the time for activity D?
a) 0 days
b) 2 days
c) 3 days
d) 4 days
e) 12 days
Question 5. What is the slack of activity D?
a) 16 days
b) 20 days
c) 18 days
d) 22 days
e) 24 days
Question 6. What is the estimated expected (mean) time for project completion?
a) 41 days
b) 70 days
c) 100 days
d) 120 days
e) 221 days
These are Project Management Planning Execution Evaluation and Control Nptel Week 4 Answers
Question 7. What is the probability that the project will be completed in 123 days? (Choose the nearest value; Use the standard normal distribution table)
a) 75.8%
b) 72.6%
c) 69.1%
d) 66.5%
e) 78.8%
Question 8. Suppose you created your activity network and discovered that you had two critical paths in your project. You share this information with another project manager, who strongly argues that a project can have only one critical path; therefore, your calculations are incorrect. What is the correct response to his assertion?
a) A project can have more than one critical path, although having multiple critical paths is also likely to increase the risk of the project falling behind.
b) Your coworker is correct; a project can have only one path. You need to return to the network and determine where you erred in developing the network logic and diagram
c) The critical path is the shortest path through the network, so more than one is not a significant problem.
d) A project can have more than one critical path, although having multiple critical paths is actually likely to decrease the risk of the project.
These are Project Management Planning Execution Evaluation and Control Nptel Week 4 Answers
Question 9. Todd is working on resource scheduling in preparation for the start of a project. There is a potential problem in the works, however, as the new collective bargaining agreement with the company’s union has not been concluded. Todd decides to continue working on the resource schedule in anticipation of a satisfactory settlement. Todd’s approach would be an example of which method for dealing with risk?
a) Accept it
b) Minimize it
c) Transfer it
d) Share it
Question 10. Suppose your organisation used a qualitative risk assessment matrix with three levels each of probability and consequences (high, medium, and low). In evaluating a project’s risks, you determine the commercial risks pose a low probability of occurrence but high consequences. On the other hand, legal risks are evaluated as having a high probability of occurrence and medium consequences. If you are interested in prioritising your risks, which of these should be considered first?
a) Commercial risks
b) Legal risks
c) Both should be considered equally significant
d) Neither is much of a threat to this project, so it doesn’t matter what order you assign them
Question 11. One common mistake made early in the risk identification process is to
a) Consider limited possibilities
b) Encourage participants to be over-optimistic
c) Support participants being over pessimistic
d) Focus on consequences and not on the events that could produce consequences
e) Give too much attention to past events
These are Project Management Planning Execution Evaluation and Control Nptel Week 4 Answers