Project Management: Planning, Execution, Evaluation and Control Nptel Week 3 Answers
Are you looking for Project Management Planning Execution Evaluation and Control Nptel Week 3 Answers ? All weeks solutions of this swayam course assignment are available here.
Table of Contents

Project Management Planning Execution Evaluation and Control Nptel Week 3 Answers (July-Dec 2025)
Course link: Click here to visit course on Nptel Website
Question 1. In reviewing the project plan, Susan sees that the first prototype must be completed by October 12. This would be best classified as a:
a) Project target
b) Limit item
c) Milestone
d) Project objective
e) Critical goal
These are Project Management Planning Execution Evaluation and Control Nptel Week 3 Answers
Question 2. The work authorization system ensures that:
a) All the work and only the work gets performed
b) Work gets performed in the right order and at the right time
c) Work is done completely and according to specifications
d) Project managers are allowed total control over project budgets and resource assignments
Question 3. The process for reviewing and accepting project deliverables is called:
a) Scope verification
b) Scope definition
c) Work Breakdown Structure (WBS)
d) Scope authorization
These are Project Management Planning Execution Evaluation and Control Nptel Week 3 Answers
Question 4. A project charter should always include:
a) The scope management plan
b) Stakeholder sign-offs
c) The business need behind the project
d) The Work Authorization documentation
Question 5. What is the total project budget in this time-phased budget?
| Activity | January | February | March | April |
|---|---|---|---|---|
| Survey | 8,000 | |||
| Design | 5,250 | 4,500 | ||
| Dirt | 6,700 | |||
| Foundation | 12,550 | |||
| Framing | 37,250 | |||
| Plumb | 7,800 | |||
| Wire | 5,500 |
a) $85,450
b) $87,550
c) $82,050
d) $86,550
These are Project Management Planning Execution Evaluation and Control Nptel Week 3 Answers
Question 6. Which of the following is a good condition for bottom-up estimating?
a) When the project involves strategic decision making
b) When the project is internal and small
c) When there is a fixed price contract
d) When there is high uncertainty involved in the project
e) When there is an unstable scope
Question 7. Which of the following is NOT one of the bottom-up approaches to estimating project time and cost?
a) Function point
b) Estimates for the WBS work packages
c) Template method
d) Range estimates
These are Project Management Planning Execution Evaluation and Control Nptel Week 3 Answers
Question 8. Estimates based on the assumption that historical data can be used as a frame of reference for current estimates are:
a) Comparative estimates
b) Ballpark estimates
c) Definitive estimates
d) Feasibility estimates
Question 9. What is the early finish time for Activity F given the activity times and precedence requirements shown in the table?
| Activity | Time | Predecessor |
|---|---|---|
| A | 5 | — |
| B | 7 | 8, A |
| C | 7 | A |
| D | 4 | A |
| E | 8 | B |
| F | 9 | C, D |
| G | 7 | E, F |
| H | — | G |
a) 15
b) 17
c) 19
d) 21
These are Project Management Planning Execution Evaluation and Control Nptel Week 3 Answers
Question 10. The AOA network of a small project is shown below. Find out the expected duration of this project.
(Values from diagram: 8, 3, 5, 6, 1, 4, 2, 4, 9, 7, 6, 3, 2, 2, 6, 5)
a) 13
b) 15
c) 20
d) 19
e) 14
These are Project Management Planning Execution Evaluation and Control Nptel Week 3 Answers