Project Management: Planning, Execution, Evaluation and Control Nptel Week 1 Answers
Are you looking for Project Management Planning Execution Evaluation and Control Nptel Week 1 Answers ? All weeks solutions of this swayam course assignment are available here.
Table of Contents

Project Management Planning Execution Evaluation and Control Nptel Week 1 Answers (July-Dec 2025)
Course link: Click here to visit course on Nptel Website
Question 1. Which of the following is NOT considered to be a characteristic of a project?
a) An established objective
b) A clear beginning and end
c) Specific time, cost and performance requirements
d) For internal use only
e) Something never been done before
Question 2. Which of the following activities is the best example of a project?
a) Processing insurance claims
b) Producing automobiles
c) Writing a policy manual
d) Monitoring product quality
e) Overseeing customer requests
These are Project Management Planning Execution Evaluation and Control Nptel Week 1 Answers
Question 3. Which of the following activities is the best example of a project? (Duplicate question as Question 2)
a) Processing insurance claims
b) Producing automobiles
c) Writing a policy manual
d) Monitoring product quality
e) Overseeing customer requests
Question 4. The commitment of financial, human, and technical resources is highest during the:
a) Conceptualization phase
b) Planning phase
c) Execution phase
d) Termination phase
These are Project Management Planning Execution Evaluation and Control Nptel Week 1 Answers
Question 5. Geoffco’s project manager names three individuals and requests a project budget of $3,000,000 for the new 8-Pod, a backpack-sized personal music player for 8-track tapes capable of holding up to 100 songs from the ’60s and ’70s. This important step takes place during which project life cycle stage?
a) Planning
b) Conceptualization
c) Execution
d) Termination
Question 6. Which of the following is NOT a reason why project management has become a standard way of doing business?
a) Increased need for skilled management of stakeholders outside of organization
b) Projects need to be done faster
c) Organizations are doing more project work in-house instead of outsourcing
d) Organizations are executing more and more projects
e) Increased product complexity and innovation
Question 7. Which of the following represents the correct order of stages within the project life cycle?
a) Planning, Defining, Executing, Closing
b) Closing, Planning, Defining, Executing
c) Defining, Planning, Executing, Closing
d) Executing, Defining, Planning, Closing
e) Planning, Defining, Closing, Executing
Question 8. All of the following are elements in the definition of a project, except:
a) A project is time limited
b) A project is unique
c) A project is composed of unrelated activities
d) A project is undertaken for a purpose
Question 9. Which of the following is NOT true when managing a portfolio system?
a) The qualities of a particular project are assessed within the context of existing projects
b) It does not require a constant effort
c) Within a small organization it can be managed by a small group of key employees
d) It requires input from senior management
Question 10. Which of the following terms is often used to denote a project that a powerful, high-ranking official is advocating?
a) Sacred cow
b) Pet project
c) Political necessity
d) Special undertaking
e) Strategic ploy
These are Project Management Planning Execution Evaluation and Control Nptel Week 1 Answers