Question 1. Which one of the following is NOT an example of a heuristic estimation technique?
a) Basic COCOMO
b) Halstead’s software science
c) COCOMO II
d) Intermediate COCOMO
e) Complete COCOMO

View Answers


Question 2. Which of the following are examples of semi-detached projects?
a) Accounting system
b) Student Information System
c) Compilers
d) Operating systems
e) Real-time system programs
f) Linkers

View Answers


Question 3. A distributed transaction processing system (TPS) for an organization having offices at several places across the country has the following modules: a database module, a graphical user interface (GUI) module, and a communication module. Which of the following COCOMO models will be best suitable for estimating the development cost?
a) Basic COCOMO
b) Intermediate COCOMO
c) COCOMO 81
d) Detailed (Complete) COCOMO
e) All of these

View Answers


Question 4. In intermediate COCOMO, if software tools are used, then the initial cost and effort estimates obtained by the basic COCOMO are
a) scaled downwards
b) scaled upwards
c) increased exponentially
d) remained unchanged
e) doubled

View Answers


Question 5. Which one of the following COCOMO II sub-models would be used when software is composed from existing parts?
a) Application composition
b) Application configuration
c) Early design
d) Reuse
e) Post-architecture
f) Pre-architecture

View Answers


Question 6. The early design model of COCOMO II is based on
a) The number of application points
b) The number of function points
c) The number of lines of code reused or generated
d) The number of lines of source code
e) The number of object points

View Answers

These are Software Project Management Nptel Week 5 Answers


Question 7. Which of the following are examples of empirical estimation techniques?
a) Expert judgement
b) Basic COCOMO
c) Halstead’s software science
d) Delphi cost estimation
e) Intermediate COCOMO
f) Complete COCOMO

View Answers


Question 8. In Halstead’s software science, the effort required to develop a program can be obtained by
a) Adding the program volume with the level of the programming language used to develop the code.
b) Subtracting the program volume from the level of the programming language used to develop the code.
c) Multiplying the program volume with the level of the programming language used to develop the code.
d) Dividing the program volume by the level of the programming language used to develop the code.
e) Raising the program volume as the power of the level of the programming language used to develop the code.

View Answers


Question 9. In the context of staffing level estimation, the time at which the Rayleigh curve reaches its maximum value corresponds to
a) Coding and unit testing.
b) Integration testing.
c) System testing and product release.
d) Product installation and delivery.
e) Regression testing.

View Answers


Question 10. Suppose the development time of a large software product has been estimated to be one and a half years. Then, in order to develop the product in nine months, what will be the total increase in development effort? (Use Putnam’s model).
a) 2 times
b) 4 times
c) 8 times
d) 16 times
e) 32 times
f) 64 times

View Answers